• 2015-11-15
  • Design of Link Road Between Sohar – Yankal Road to Sham Project, Sultanate of Oman
  • Project Location:

    The project is located in Sohar.

    The Scope of Work is detailed as follows:

    According to the ToR, the Scope of Work is divided into phases as follow

    • Design Link Road between Sohar-Yankal Road to Sham (15km).
    • Design of access road to Seeha A1 Barrier (4km)

    1. Feasibility Study

    • The study shall be based on relevant data and information connected with the specific project and location. The designer shall describe project is practically establish in the location or if not, with reasons and option. The corridor study shall guide the options or alternative way/route with most effectively designs alignment to serve the more citizens in the area.

    2. Preliminary Design

    • Following approval of the feasibility study, the consultant shall carryout preliminary design including all associated works and the consultant shall develop various alternatives and recommend the most effective and economical engineering solution with facts and cost comparisons of various alternatives.

    3. Final Design

    • Following the approval of th preliminary Design and instructed by the client, Consultant shall prepare a detailed design, detailed tender documents, cost estimate to cover all the components of the projects in accordance with the requirement of topographical survey, structures protection, landscaping & lighting.